This tutorial takes you from the model you receive to a bill you can sign. It uses the eight QSKing 5D Quick Start videos and a sample model you can download and check yourself. It starts with the first question the AIQS / NZIQS BIM Best Practice Guidelines ask: is BIM part of your appointment?
1. Is BIM part of your appointment?
The AIQS and NZIQS BIM Best Practice Guidelines (sections 2.1 and 2.2) separate two kinds of project. QSKing 5D works on both, because it reads IFC, which every major design program exports. What changes is what you can ask the designers for, and how far you can rely on the model.
BIM is in your appointment
- Give your requirements to the BIM Execution Plan (BEP) before modelling starts: what you need measured, in which units, and at which stages. The NATSPEC National BIM Guide (7.2) asks the QS for this input when cost management is one of the project’s BIM uses.
- Ask for every IFC to be exported with the QSKing QTO setup (step 2 below), and write it into the BEP.
- You may also receive the native Revit model. With QSKing QTO Plugin for Revit you can measure it directly and compare the result with QSKing 5D.
BIM is not in your appointment
- Ask the designers for an IFC export. Send them video 2 and the checklist in 4.1.1 Preparing IFC models. It takes them a few minutes.
- The model was not made for costing, so expect gaps. QSKing 5D shows you what it could not measure and why, and you record your own decisions (step 5).
- Ask before you pass the model on to anyone else, as the Guidelines advise.
Settle these on either kind of project
- The model’s status as issued, for example “for information” or “for pricing”.
- Whether you may rely on it for quantities.
- Who owns your outputs, such as the cost plan.
- Whether you may process the model with your own software and tools.
These are questions to raise, not legal advice: your contract decides. Section 7.1 of the Guidelines lists more.
2. Try it on the sample model
The sample model is a small substructure, modelled in Revit 2027 and exported with the QSKing QTO setup: pad footings, pile caps on bored piles, ground beams, a lift pit and core, a wall footing with a retaining wall, and a slab on ground. The dimensions are round numbers, so every quantity is easy to check by hand. Download the sample model and hand check (free, version 1.4, 13.7 MB: the Revit model, its IFC export, the QSKing 5D project with its Project Basis set, the six structural drawings, the 2D projects from Quick Start 9 and 2D Tutorial 1, a README and the hand check workbook).
Step 1 – Install and start the free trial
Video 1: Install and free trial (1:39). Download QSKing 5D and start the 30-day trial.
Step 2 – Ask for the right IFC
Video 2: Exporting the IFC from Revit (1:39) and the checklist in 4.1.1 Preparing IFC models. Try it: open the sample .ifc file in Notepad and search for IFCELEMENTQUANTITY. It is there because base quantities were exported. A file without it is the first thing to raise with the designer.
Step 3 – Start a project and load the model
Video 3: New project and Manage Links (1:31). Start a project and load the sample IFC. On a real project, load each consultant’s model. (The download also has the finished project, QS video.qs5d: keep it in the same folder as the IFC and open it to compare with your own.)
Step 4 – Run QTO
Video 4: Run QTO (1:27). For the sample, tick Excavation and enter Hardcore 100 mm and blinding 50 mm under Excavation settings, as in video 8.
Step 5 – Check what the model can and cannot support
Video 5: The QTO Schedule (1:43), then:
- In the QTO Schedule, pick any line and read its System Note: how it was measured, and what was left out and why.
- Open the Coverage Audit from the schedule. Every element in the model is listed: measured and linked to the bill, measured but not linked, recorded by you, or not accounted for, with the likely reason.
- Where the model falls short, record your decision: Excluded, Deemed included or Model error. Model errors are what you raise with the designer.
- Where the model does not say what something is, say it yourself: select the elements and use QS Settings ▾ → Set SubType (for example Ground beam) or Set Excavation RL. Your choice is saved in the project, not in the IFC, and stays with the elements when the next issue is loaded. In the sample model the ground beams already carry their SubType from Revit.
- Generate certificate: one A4 sheet with the coverage, the models, the issue dates and your decisions, signed Prepared by and Checked by.
- Set the Project Basis before you generate the certificate or export the BQ: Manage tab > Project Setting, choose the engagement, then Use the suggestion and OK. Until it says what the quantities are taken from, QSKing 5D will not issue the certificate or the BQ (Run QTO and billing work without it). Sample model 1.2 and later have it set; if you downloaded 1.1, set it yourself.
Step 6 – Check it by hand
Video 8: Substructure you can check (6:47). Follow along with the hand check workbook from the download: every substructure quantity is checked by hand, and QSKing QTO Plugin for Revit and QSKing 5D give the same answer. If you have Revit, open the .rvt from the download with QSKing QTO Plugin for Revit, run QTO with the same excavation settings and compare the two schedules yourself.
Step 7 – Bill and price
Video 6: Workbook and Export BQ (1:47). Link the quantities into the bill, price it and export it to Excel. The button is now called Export Report; it needs the Project Setting answered first (step 5).
Step 8 – The next issue
Video 7: A new model issue (1:25). Load the next issue: the bill updates, with a change report to review.
Videos 1 to 7 follow Autodesk’s Snowdon Towers sample project; video 8 uses the sample model above. All videos are listed on QSKing 5D Quick Start videos.
3. Read next
- Certainty & Accountability: the five principles behind every quantity.
- 3.1.3 QSKing 5D UI and 4.1.2 Run QTO in QSKing 5D: the detail behind each step.