Export the open Workbook to Excel, as a Cost Plan or as a BQ, ready to issue.
Export Report is on the Output panel of the 2D tab and the 3D tab. It was called Export BQ before release 1.0.27.
The button
- Click the icon to export this project’s own report: a Cost Plan when the Service is 1 Cost Planning and Estimates (and a Cost Plan can be printed), otherwise a BQ.
- Click the lower half (▾), or right-click the button, to choose Cost Plan or BQ yourself.
- The Workbook pane has the same two choices on its Export Report → button.
To export
- Open the Workbook you want to issue (Workbook).
- Click Output › Export Report, or choose Cost Plan or BQ from its ▾.
- Choose where to save it. The file is named after the report, the project and today’s date, for example QTO_CostPlan_Snowdon_2026-11-23.xlsx or QTO_BQ_Snowdon_2026-11-23.xlsx.
- Click Yes to open it in Excel.
BQ
The bill of quantities. The Excel workbook holds the Summary, a bill for each element, and the Collection, with the Project Setting’s basis and your source decisions.
Cost Plan
The same file, with its first sheet made the Cost Plan Summary. That sheet adds:
- the GFA line under the project basis, saying where the GFA came from: the Area Schedule, the sheets it was measured on, or the source of a typed area. For example: GFA 1,310.00 m² (FECA 1,250.00 + UCA 60.00) — Area Schedule; measured on A101 Issue 2;
- the GFA cell: “GFA (m²)” in column D and the GFA in column E;
- a $/m² GFA column: an Excel formula on every total, every subtotal and the GRAND TOTAL, each dividing by the GFA cell, so it stays right if you change the figures in Excel;
- AIQS group subtotals: Substructure, Superstructure, Finishes, Fittings, Services, External Works and External Services, each an =SUM of its group’s rows. They are not added into the GRAND TOTAL, which stays the bill’s own figure. If your Workbook already has its own =SUM rows, none are added;
- a line when the GFA has changed since the last Cost Plan.
The sheet is set up to print on A4 portrait, one page wide.
What a Cost Plan needs
- An elemental Workbook, with AIQS element rows (PR … YY), for example one started from the AIQS Elemental Cost Plan template. A trade Workbook prints a BQ only.
- The GFA. Measure it first with Area (Measurement › Area ▾ › Area Plan), or type an area in the Area Schedule.
Until both are there, Cost Plan is grey, and its tip says which one is missing and what to do. BQ is never greyed for these reasons. A Cost Plan can be exported in any Service, not only in Cost Planning.
Each Cost Plan records its GFA
When a Cost Plan is exported, QSKing 5D keeps the GFA it used. The status line says Cost Plan exported (GFA … m²). Save the project to keep its record. The Area Schedule then shows Last Cost Plan: …, GFA … m², and GFA changed since the Cost Plan of … if the GFA moves after it.
When the export waits
A BQ or Cost Plan cannot be issued until:
- Quantities taken from is chosen in Project Setting; and
- every item measured from both the drawings and the model has an answer in the Source Check.
QSKing 5D says which is missing. Export QTO (the QTO Schedule as it stands) is not a BQ and is never held up.
In the Revit plugin the button is also called Export Report. Cost Plan is grey there: it is printed in QSKing 5D, where the GFA is measured.