State the basis the project is measured on: is the BIM model part of your service agreement, and so where are the quantities taken from.
Every project has a Project Setting. It is saved with the project and printed on the certificate and the BQ. A new project opens it straight away, and you can open it again at any time.
To set up a project
- Click Manage tab › Manage Project panel › Project Setting, as Revit’s Project Information.
A click on the Service in the middle of the top bar opens it too. When you start a new project, it opens by itself. - On the Basis tab, answer Is the BIM model part of your service agreement?
- Yes: the model is a contract deliverable. Choose the Platform (Revit, ArchiCAD, Tekla, or IFC from other software). The quantities are taken from the model.
- No: the model is for information only. The quantities are taken from the drawings.
- On the Services tab, answer Which Service are you starting? It is required: pick one. QSKing 5D is arranged around the four Services of Cost Management, in order:
For each Service you can also tick In appointment and give its Budget hours; both are optional. The Service shows in the middle of the top bar, on blue (for example 2 BQ). Click it to open Project Setting and change the Service.Service Now 1 Cost Planning and Estimates Built 2 BQ Built 3 Valuation and Variation Grey: coming, not built yet 4 Final Account Grey: coming, not built yet - On the Project tab, fill in the Project Name, Project No. and Location (all three are required, marked *), and the Notes (the client, and anything else about the project). With Yes, also the Model source (who made the model, and which issue) and the Model status. The Home page’s card for the project shows its Project Name, Project No. and Service.
- Click OK.
QSKing 5D opens the tab that fits the answer: the 2D tab when the drawings govern, the 3D tab when the model governs.
What the Service changes
- In 1 Cost Planning and Estimates, Area ▾ is live, so the GFA can be measured, and Export Report’s icon exports a Cost Plan. Auto-bill is grey: it bills to ANZSMM, which is BQ work.
- In 2 BQ, Auto-bill is live, Area ▾ is grey, and Export Report’s icon exports the BQ.
To take the quantities from somewhere else
Most projects need only the one answer. When a part of the job is measured from the other source, click Change… beside the quantities line:
| Quantities taken from | Means |
|---|---|
| The model governs | 2D is used only for work that is not modelled. |
| Drawings govern | The model is an aid and a check. |
| Model and drawings complement each other | Work is measured from whichever shows it, and both are billed. |
- Decided by: your name. It is recorded with the date, under the quantities line.
- Except for: pick an Element or a Trade and the other source, then Add. For example: the model governs, except SB Substructure from the drawings.
A project saved before release 1.0.23
A project with no complete Project Setting still opens. QSKing 5D asks once whether to open Project Setting now. If you say No, measuring works as before, but the BQ and the certificate cannot be issued until Quantities taken from is chosen.
Next: Drawing Register to add the drawings.
The answer follows the AIQS/NZIQS BIM Best Practice Guidelines (s. 2.1 and 6.2).