Measure the building’s areas on the drawings, and get the GFA for a cost plan.
Area ▾ is on the Measurement panel of the 2D tab, after Set Dimension Group. It is live when the Service is 1 Cost Planning and Estimates. In any other Service it is grey, and its tip tells you to change the Service first in Project Setting (Manage tab).
The three choices
| Choice | What it does |
|---|---|
| Area Plan | Starts an area plan for one scheme and one level, on the sheet that is open. |
| Area | Measures on the open sheet’s area plan. Grey when no sheet is open. |
| Area Schedule | Opens the Area Schedule pane: FECA, UCA and GFA by level, with the GFA history. |
To measure the GFA
- Open the plan sheet for a level.
- Click Measurement › Area ▾ › Area Plan.
- Choose the scheme (FECA or UCA) and the level. The level is offered from the sheet’s Level; the sheet is the open one. Both a level and a sheet are needed.
- Click OK. QSKing 5D makes the plan and a Dimension Group for it, under Building areas (for example FECA — Level 1), and goes straight to Area.
- Trace the area with Measure Area, as in Pick & Choose: snapping and cut-outs work as usual.
- Repeat for UCA, and for each level.
If you start the same scheme and level twice, QSKing 5D opens the plan already made and says so. Next time, Area ▾ › Area on that sheet picks its plan for you, and asks which one when there are two, for example FECA and UCA.
Each area is an ordinary measured line on a named sheet, with its System Note. It is not priced.
The Area Schedule
A pane like the QTO Schedule, beside the drawing. It refreshes after each measurement. It shows:
- for each level: FECA, UCA and GFA = FECA + UCA (AIQS), with the source: the sheets measured on, or typed — source: …;
- totals, and the number of storeys (counted from the levels with a GFA, unless you type it);
- UFA, the functional unit and the function quantity, which you can type;
- Add typed area…, for a cost plan started from an architect’s area schedule. A measured figure wins over a typed one for the same level and scheme;
- the GFA history: each time a level’s GFA moves, one line with the date, the level, old → new m², the sheet and who. Add reason… lets you say why;
- after a Cost Plan export, Last Cost Plan: …, and GFA changed since the Cost Plan of … if it has moved since.
In the Project Browser
Area plans are listed under Area Plans › FECA / UCA › one entry for each level (for example Level 1 — A101). Double-click an entry to open its sheet. Right-click it for Area or Area Schedule.