Measure the building’s areas on the drawings, and get the GFA for a cost plan.

Area ▾ is on the Measurement panel of the 2D tab, after Set Dimension Group. It is live when the Service is 1 Cost Planning and Estimates. In any other Service it is grey, and its tip tells you to change the Service first in Project Setting (Manage tab).

The three choices

ChoiceWhat it does
Area PlanStarts an area plan for one scheme and one level, on the sheet that is open.
AreaMeasures on the open sheet’s area plan. Grey when no sheet is open.
Area ScheduleOpens the Area Schedule pane: FECA, UCA and GFA by level, with the GFA history.

To measure the GFA

  1. Open the plan sheet for a level.
  2. Click Measurement › Area ▾ › Area Plan.
  3. Choose the scheme (FECA or UCA) and the level. The level is offered from the sheet’s Level; the sheet is the open one. Both a level and a sheet are needed.
  4. Click OK. QSKing 5D makes the plan and a Dimension Group for it, under Building areas (for example FECA — Level 1), and goes straight to Area.
  5. Trace the area with Measure Area, as in Pick & Choose: snapping and cut-outs work as usual.
  6. Repeat for UCA, and for each level.

If you start the same scheme and level twice, QSKing 5D opens the plan already made and says so. Next time, Area ▾ › Area on that sheet picks its plan for you, and asks which one when there are two, for example FECA and UCA.

Each area is an ordinary measured line on a named sheet, with its System Note. It is not priced.

The Area Schedule

A pane like the QTO Schedule, beside the drawing. It refreshes after each measurement. It shows:

  • for each level: FECA, UCA and GFA = FECA + UCA (AIQS), with the source: the sheets measured on, or typed — source: …;
  • totals, and the number of storeys (counted from the levels with a GFA, unless you type it);
  • UFA, the functional unit and the function quantity, which you can type;
  • Add typed area…, for a cost plan started from an architect’s area schedule. A measured figure wins over a typed one for the same level and scheme;
  • the GFA history: each time a level’s GFA moves, one line with the date, the level, old → new m², the sheet and who. Add reason… lets you say why;
  • after a Cost Plan export, Last Cost Plan: …, and GFA changed since the Cost Plan of … if it has moved since.

In the Project Browser

Area plans are listed under Area Plans › FECA / UCA › one entry for each level (for example Level 1 — A101). Double-click an entry to open its sheet. Right-click it for Area or Area Schedule.

In Cost Planning with no GFA yet, the status line gives the first task: Measure the GFA first: Measurement › Area ▾ › Area Plan. Nothing is blocked. To reshape an area later, see Adjust on sheet.