Every measured line in one list, and the Bulk Check: the model and the drawings side by side, on the figures a QS bulk-checks a frame by.

The QTO Schedule is the pane beside the 3D view and the drawings, in QSKing 5D and in the QSKing QTO Plugin for Revit®. It fills after Run QTO (the model’s lines) and as you measure on the drawings (the drawings’ lines).

The list

  • One flat list of lines: no Trade → Element headings to open and close.
  • Search on the filters’ row keeps up as you type. A line under the filters says what they hide.
  • From: Drawings, Model or All sources. A project opens on the source that governs it (Project Setting). After Run QTO it shows All sources, so the new model lines are seen; its words still say which source governs.
  • This sheet and Selected in view narrow the list to what you are looking at. More filters holds the rest.
  • Tools ▾, beside Workbook, holds the line tools: Export QTO, View Element Details, Show Properties, Show in 3D, Isolate in 3D, Source View and Coverage Audit. Show in 3D and Isolate in 3D are grey on a line measured on a drawing; Source View opens its sheet.

The Bulk Check

In the QTO Schedule, the ▾ Bulk Check button opens it and ▸ Bulk Check folds it to one line, to see more lines of the schedule. Folded, the line reads, for example, Bulk Check (model / drawings): …. After Run QTO the status line adds how many cards are the same and which differ.

Each card is a small table:

ItemModel (3D)Drawings (2D)Check
Total concrete2.92 m³2.92 m³same
Total formwork6.5 m²—model only

Check says same when the difference is within 0.5 % of the larger figure, or the difference as the drawings against the model (drawings +1.0 %). A side with nothing measured reads model only or drawings only; its column heading says — none loaded or — none measured. A figure that is not measured shows —, never 0. Hover a row: its tip says what was counted and how many lines.

The cards

CardTotalUnder it
Total floor areaGround slab + floor slabs, plan area, as measured. The roof slab is not a floor.QSKing 5D: the Area Schedule‘s GFA, for information only. It is not the floor area and is not used in the ratios.
ConcreteTotal concrete, m³ (Trade 6 Concrete or Material concrete), walls included.Beams ÷ floor area and columns ÷ floor area, m³/m².
FormworkTotal formwork, m².Beam formwork ÷ beam concrete, m²/m³.
ReinforcementTotal, t.kg per m³ of each element’s own concrete: footings, ground slab, columns, floor slabs, beams, walls, roof slab, roof beams.
Structural steelTotal, t: length × kg/m from the Steel Section Library, or t / kg lines.Steel ÷ floor area, kg/m².
Design to costRevit plugin only: Quantity × the Revit type’s Cost, for modelled elements. Grey in QSKing 5D; price in the Workbook there.

A ratio shows on a side only when both its parts are measured on that side. Floor slabs and beams mean those below the roof; a roof member that cannot be told apart stays with them, and the card says so. Reinforcement whose element cannot be told is in the total, not in a kg/m³ row.

Key in a reinforcement rate

Where reinforcement is not measured on a side, its row offers Key in….

  1. Click Key in… on the row (for example Footings, Drawings (2D)).
  2. Type the rate in kg/m³ of that element’s concrete (1 to 1,000), and its source, for example Engineer’s rate, S-001 note 4. The source is required.
  3. Click OK. The tonnes follow: rate × that element’s measured concrete, added to the total reinforcement.

A keyed rate shows typed (the total part typed); its tip gives the source, who and when. Its check reads typed — not measured: it is never same. Open the same row to change it, or Remove it. When a measured figure comes (a new Run QTO or a measured line), the measured figure is used and the row says so.

The rate is saved with the project: in QSKing 5D in the project file, with a line in the Activity Log; in the Revit plugin in the model, when you save it.

The Bulk Check measures both sides the same way, so a difference points to a line to look at, not a rounding. Export QTO carries the same figures in its Summary sheet.